Ladue Public Works Department

Ladue Public Works Department

 

CURRENT PUBLIC WORKS PROJECTS

 

PUBLIC WORKS PROJECT UPDATES –November 2019


Stormwater Management Program (SWMP) – Implementation Plan Project Updates  For more information, visit the Public Works page: https://www.cityofladue-mo.gov/departments/public-works-department-214


Willow Hill – Reroute Along Road (infrastructure), HR Green
The design phase began on 7/2/18. Public information meetings were held in August & September 2018, then follow up resident meetings were held. The preliminary design was approved by MSD and a project update was presented to the public on October 8, 2019. Now, the City is in the process of obtaining the required easements for the project. Once all of the easements are obtained, the final plans and project specifications will be completed, and the project will be bid. Construction is anticipated for 2020.


Robin Hill Lane/McKnight Lane Bank Stabilization, Intuition & Logic

The design phase began on 7/2/18. Public information meetings were held in July and October 2018 and sixteen follow up property owner meetings took place since that time. The preliminary plans were approved, and easement documents are being prepared. Easement acquisition will begin in early 2020. Construction is scheduled for late 2020.


Deerfield/Wakefield storm sewer improvements, HR Green
The design phase began on 7/23/18. Preliminary design has been taking place. A Public Informational Meeting will be scheduled in late 2019. This project will be constructed in two or three phases over the next several years.


South Tealbrook Drive storm sewer improvements, Hart Engineering
The design phase began on 7/2/18. A field review was completed, meetings with the impacted residents impacted has occurred, the preliminary plans were approved by MSD, and easements are in the process of being acquired this fall. Construction is scheduled for 2020.


Babler Lane storm sewer improvements, EDM
The design phase began on 9/24/18. A Public Informational Meeting was held on January 29, 2019 at Ladue City Hall where the pipe alignment was presented. MSD has provided comments on the preliminary design and additional design work is required to meet the requirements of MSD. Easement acquisition will occur in 2020 and Construction is scheduled for late 2020.


Traffic Studies
The Cities of Ladue & Brentwood hired CBB, the cities on-call traffic engineering consultant, to conduct a study of McKnight Road between Litzsinger and I-64. A joint public open house meeting took place on May 15, 2019 in Tilles Park to obtain feedback from the public about their concerns. All of the public feedback was compiled and analyzed, and the consultant identified potential solutions for implementation. Those solutions were presented to the public at a second public meeting which was held on October 30, 2019. The public comment period will be open until November 15, 2019. Then, CBB will review the public comments and produce a final report to both cities.


The City of Ladue is working with CBB, the cities on-call traffic engineering consultant, for a study on Warson Road at Conway Road & Ladue High School and the nearby vicinity. Concerns in this area include high traffic volumes including Ladue High School traffic, traffic back-ups at the intersection, delays in turning from side streets onto Warson Road, and neighborhood cut-through traffic. The study began in January 2019 with a kick-off meeting. CBB collected data. The first Public Information Meeting took place on March 12, 2019 and over 20 households were represented. CBB analyzed the data that has been collected and the ideas and concerns presented by the public and presented their findings to the City and Public at a second Public Open House meeting which was held on July 18, 2019. The four options that were presented included a round-a-bout, a mini round-a-bout, a traffic signal without the addition of turn lanes, and a traffic signal with the addition of turn lanes. The Public Works Committee recommended that one of the signalization options be implemented. The Final report for the study will be submitted to the City in Fall 2019.


ADA Self-Evaluation and Transition Plan
The City has begun the implementation phase of the ADA transition plan which identified both sidewalk and facility improvements that are in need of modification in order to work toward ADA compliance. The first project in the ADA implementation plan was the sidewalk modifications to Clayton Road in the Business District between I-64 and Conway Road which were completed Summer 2019. The next project now under design by Oates Associates, includes ADA sidewalk improvements on Clayton Road, west of Warson Road. The City will continue to improve the sidewalks on Clayton Road over the next several years.


Dielman Road Improvements
The City applied for Federal Funds for Dielman Road Improvements in February 2019 and learned that the application was successful. The City participated in the East-West Gateway Council of Governments Open House on July 9, 2019 then after EWGCC Board approval in August 2019, the City will execute a program agreement with MoDOT, who administers federal funds on behalf of FHWA, this fall. Design will begin in 2020. Dielman Road is one of two remaining roads identified for sidewalks in the 2012 Sidewalk Implementation Plan. Sidewalks will be installed on the west side of Dielman between Ladue Road and the northern municipal boundary near Tamarack. Improvements to the pavement will also be part of the project. The sidewalk will connect to sidewalks that have been installed in Olivette on Dielman Road. Federal Funding will pay for 80% of the right-of-way and construction costs.


Edie’s Mulch Site
The City applied for and obtained a Municipal Park Planning Grant to develop a master plan for the 14.5-acre site which is currently being utilized as a transfer station for the City’s leaf and mulch program on approximately 3 acres of the site. The property is located off S. 40 Drive and is along the Deer Creek corridor. The property will be significantly impacted by MSD’s Deer Creek Sanitary relief sewer project. The park planning kick-off meeting was held on April 2, 2019 with staff, the park planning consultant (SWT), and the BOSTA (Beautification, Open Space, and Tree Advisory) Board. The first of two public meetings were held on March 14, 2019 with 36 residents in attendance. The concepts include a linear trail through the property with benches, two shelters, and plantings. There is also a survey link on the website public input can be submitted. The second meeting took place on June 24, 2019 from 5:00 – 7:00 pm and a refined design was presented. Information from both presentations can be found on the Public Works page of the City’s website. SWT presented the Master Plan to City Council at the September 16, 2019 meeting and adopted the Master Plan for the property.


Public Works In-house Maintenance Programs
• Brush Collection (monthly: March – September plus Christmas tree pick-up in January)
• Leaf Collection (October – December & April)
• Parks & Grounds (Rodes Park, planters, municipal campus, Beautify Ladue landscape maintenance, Edie’s Mulch Site, Centennial Trail)
• Pavement and Sidewalk Maintenance (crack sealing, pothole patching, sidewalk removal & replacement, snow and ice removal)
• Bridge & Culvert Maintenance
• Vegetation Management on Right-of-Way (mowing, trimming, honeysuckle management, tree removal)
• Fleet & Building Maintenance 

 

 

City of Ladue

 




Storm Water Funding Application

Program Eligibility and Information

 (hard copies can be found at the Public Works Office)

 

Project contacts:

Corrected Project email address:    laduestormwater@hrgreen.com 

Project phone number: 636-812-4222

Storm Water Management Program - Report of Finding

 

City of Ladue- Storm Water Engineering Manager

Pete Merten - 314-993-5665
pmerten@cityofladue-mo.gov

 

 

Storm Water Funding Application

Program Eligibility and Information

DID YOU KNOW?

Do you have questions or want to know more about the Public Works Department? Click the links below:

CONTACT

Ladue Department of Public Works
9345 Clayton Rd
Ladue, MO 63124

(314) 993-5665
alamitola@cityofladue-mo.gov

publicworks@cityofladue-mo.gov

Upcoming Events

November 18
City Council Work Session
3:00 PM
9345 Clayton Road City Council Chambers
November 18
City Council Meeting
4:00 PM
9345 Clayton Road
November 20
Zoning and Planning
4:00 PM
9345 Clayton Road
November 21
Architectural Review Board Meeting
8:30 AM
9345 Clayton Rd. - City Hall Council Room
November 28
Thanksgiving
12:00 AM
View Full Calendar